Monday, February 22, 2010

Snow slows but does not hinder the renovation of the Lane University Center.



With near record snowfall crippling campus for over a week, the progress of the renovation has continued. With rough-ins progressing for the duct work, plumbing, and electric work is continuing nicely with the project. Outside work is on hold until the weather clears so as it warms up look for work on the expansion of the Lane Center to continue.

Thursday, February 4, 2010

Progress Meeting # 8

At today's renovation progress meeting, it was announce that we have 329 days remaining in the project. That seems like so many days away but it really will be here before we know it. The good news is the contractor is right on schedule and the work is moving forward rapidly As you can see from the attached pictures here, erection of the steel is moving along. Actually, the outline of the building is up and the contractors began putting up the roof joist yesterday.



The demolition inside the building is ongoing in the building and work inside is beginning to take shape as well. The duct work, electric, and plumbing aspects of the renovation have begun inside. More work to come in these areas over the next two weeks.